| Fiscal year | NPR | Description | Total Grant Amount | Discretionary Funding | Entitlement Funding |
| 2005 |
44 |
Remove Obstructions |
$236,036 |
$0 |
$236,036 |
| 2005 |
17 |
Construct Utilities |
$1,510,630 |
$0 |
$1,510,630 |
| 2005 |
45 |
Extend Runway |
$367,719 |
$0 |
$367,719 |
| 2005 |
46 |
Construct Taxiway |
$896,936 |
$0 |
$896,936 |
| 2005 |
20 |
Construct Access Road |
$472,072 |
$0 |
$472,072 |
| 2005 |
38 |
Expand Apron |
$94,414 |
$0 |
$94,414 |
| 2006 |
39 |
Install Miscellaneous NAVAIDS |
$75,000 |
$0 |
$75,000 |
| 2006 |
41 |
Construct Apron |
$384,000 |
$0 |
$384,000 |
| 2006 |
66 |
Rehabilitate Runway Lighting |
$250,000 |
$0 |
$250,000 |
| 2006 |
45 |
Extend Runway |
$2,091,000 |
$686,773 |
$1,404,227 |
| 2007 |
46 |
Construct Taxiway |
$775,000 |
$775,000 |
$0 |
| 2007 |
42 |
Install Weather Reporting Equipment |
$150,000 |
$0 |
$150,000 |
| 2007 |
38 |
Install Perimeter Fencing |
$600,000 |
$0 |
$600,000 |
| 2008 |
41 |
Construct Apron |
$400,000 |
$0 |
$400,000 |
| 2008 |
62 |
Update Airport Master Plan Study |
$85,000 |
$0 |
$85,000 |
| 2008 |
45 |
Install Runway Vertical/Visual Guidance System |
$20,000 |
$0 |
$20,000 |
| 2008 |
38 |
Install Apron Lighting |
$10,000 |
$0 |
$10,000 |
| 2008 |
39 |
Install Miscellaneous NAVAIDS |
$8,760 |
$0 |
$8,760 |